Mains Gas Replacement in Leeds
Project Description
SCD was engaged in the extensive 2.5 km mains gas replacement throughout Leeds. Our fully accredited main laying teams were complemented on site by a full-time project manager and support personnel.
SCD worked on a £2m term contract replacing gas mains and services infrastructure in line with the HSE guidelines
As part of this contract, SCD completed diversion works on the East Leeds ring road installing 2.5km of 355mm and 180mm mains and services.
The project was completed ahead of the programme and on budget.
Our fully accredited main laying teams were complemented on-site by a full-time project manager and support personnel, with the mains and services tested and commissioned in line with the latest engineering standards.
The three-month project was undertaken on nights to ensure disruption to the busy interchange was kept to a minimum., and the detailed planning and close liaison with all parties resulted in the scheme being delivered ahead of the programme.
Project Summary
Installation of mains and services gas pipework.
Commissioning and testing of gas pipework.
Reinstatement of pathways and carriageways in accordance with NRSWA.